Monday, July 24, 2006

INtools Tips & Trick: 2 Cases of Process Data

As you know, sometimes Process Engineer define several cases in the Material Balance.
For example Case 1 is used for Normal Condition and Case 2 is for Other Condition.

Intools has capability to record process data of this different cases very well.
It also can be calculated and create report separately for each cases.

How to do it?

Let's open the Process Data Module.
1. Open a required Tag. No.
2. Complete the process data as required.
3. After finish click Save.
4. Click Action>Enable Case...

Fig.1 Enable Case


5. Then a pop up window like Fig. 2 will occur...


Fig. 2 Governing Case

6. Click OK and then select a name/number of Case it will be (or you can create and define a number/name also)...

Fig.3 Enable Case


Fig.4 Cases

7. Select a case, then click OK and save it. It will be saved as your Governing Case.
8. Now we will add another case. Click Action>Add Case


Fig.5 Add Cases

9. Select a number/name of case.
10. Modify the process data as necessary, then click save.
11. If you check the first row of the process data, then in the drop down menu, you'll find that now you have two cases. Select any case you want to see the different.

-fe-